Assembly instructions
Mono-pitch patio roof: step by step.
One action per step. Large numbers, pictures of the tools, warnings for anything that can go wrong. With two people you can build the roof in about a day.
- 2 peopleper instructions
- approx. 1 daydepending on project size
- 88 stepswith done checkmarks
Before you start
What you need
- 2 people
- approx. 1 day depending on project size
- Water supply and power supply nearby
- Work gloves, safety shoes, work trousers
- Clean the roof every six months.
Caution
- Electrical installations (LED) only by qualified installers. Otherwise the warranty lapses.
- The user is responsible for correct installation and use. Observe local laws and regulations.
- Never carry or lay glass alone.
Tools (all chapters)
- Cordless screwdriver
- Hammer drill
- Spirit level
- Tape measure
- Mitre saw
- Screwdriver
- Metal drill bit
- Masonry drill bit
- Driver bits
- Hole saw
- Trestles
- Ladder
- Props
- Hammer
- Hacksaw
- Utility knife
- Cartridge gun
- Gloves
- Safety shoes
- Work trousers
Good to know: snow load and depth
- Snow load 16 mm polycarbonate
- approx. 75 kg/m² (sheet width 1000 mm)
- Snow load 8 mm laminated safety glass
- approx. 85 kg/m² (sheet width 700 mm)
- Snow load 10 mm laminated safety glass
- approx. 95 kg/m² (sheet width 700 mm)
- Support needed from depth (without reinforced rafters)
- Polycarbonate 4.5 m, glass 4.0 m: cross beam with additional posts
- Maximum depth with steel rafter inserts
- Polycarbonate 6.05 m, glass 5.05 m
- LED spot
- 12 V DC, max. 3 W, IP65, Ø 36 mm × 27 mm, cable 6 m
Times per step are guide values for two people (about 9 hours in total). Example dimensions: roof 6060 mm wide, 3000 mm deep, 8 bays. Always calculate with your own dimensions.
All steps to take along
Mono-pitch patio roof: installation step by step. 2 people, approx. 1 day depending on project size (as stated in the instructions). Times per step are guide values for two people.
01 Tools and materials
- Cordless screwdriver
- Hammer drill
- Spirit level
- Tape measure
- Mitre saw
- Screwdriver
- Metal drill bit
- Masonry drill bit
- Driver bits
- Hole saw
- Trestles
- Ladder
- Props
- Hammer
- Hacksaw
- Utility knife
- Cartridge gun
- Gloves
- Safety shoes
- Work trousers
Parts: Fixing material for your house wall (not in the kit), Screws for the floor (not in the kit)
-
1.1 Lay out power tools: cordless screwdriver, hammer drill, mitre saw.
-
1.2 Measuring and drilling: spirit level, tape measure, metal and masonry drill bits, driver bits, screwdriver.
-
1.3 Lay out the hole saws: 44 and 76 mm. With a roof overhang you need 83 mm.
Caution: The hole saws are for the LED, leaf guard and drain pipe.
-
1.4 Get the aids: trestles, ladder, props, hammer, hacksaw, utility knife, cartridge gun.
-
1.5 Put on protective clothing: work gloves, safety shoes, work trousers.
-
1.6 Make sure a water supply and a power supply are nearby.
-
1.7 Buy screws and wall plugs for your house wall and the floor at a DIY store.
Caution: This fixing is not part of the kit. Get advice on your wall type.
02 Unpack and check
- Utility knife
- Gloves
Parts: Kit, Packaging and film
-
2.1 Take the kit out of the packaging carefully and properly.
-
2.2 Compare all parts with the parts overview.
-
2.3 Check for visible defects and transport damage.
Caution: If something is missing or damaged: report it to us immediately.
-
2.4 Collect the film and packaging and dispose of them correctly.
Caution: Please do not leave the film lying around: dispose of it responsibly.
03 Parts overview
Parts: Wall profile, Gutter, Rafters (side beams and intermediate beams), Posts, Wall trim, End caps for gutter and wall
-
3.1 Profiles: wall profile, gutter, rafters, posts, wall trim.
-
3.2 Gutter and wall: end caps, stop angles, leaf guard, wall caps.
-
3.3 Water drainage: drain pipe DN75, pipe bend, leaf guard.
-
3.4 Fixing: floor profile, wall fixing, screws, silicone, sealing tape, end seal.
-
3.5 Roof covering: polycarbonate or glass, plus 2 mm rubber (4 mm for glass).
-
3.6 Polycarbonate only: anti-dust tape and aluminium end profile. polycarbonate only
-
3.7 Optional: LED set with spots. optional
04 Calculate dimensions
- Tape measure
- Spirit level
Parts: Example: 6060 mm wide, 3000 mm deep, 8 bays
-
4.1 Remember: the roof falls 14 cm per metre (8 degrees).
Caution: The slope always runs from the wall to the gutter.
-
4.2 Fix the height at the gutter. Example: 200 cm.
-
4.3 Set the wall profile higher: 3 m depth × 14 cm = 42 cm more.
-
4.4 Result: bottom edge of the wall profile at 242 cm.
-
4.5 Check the depth: from 4.5 m (polycarbonate) or 4.0 m (glass), the roof needs a cross beam with additional posts.
Caution: This applies if the rafters are not reinforced. With rafter inserts, 6.05 m (polycarbonate) and 5.05 m (glass) are possible.
-
4.6 Calculate the rafter spacing: (roof width − 60 mm) ÷ bays. Example: (6060 − 60) ÷ 8 = 750 mm.
-
4.7 Length of the roof covering: roof depth − 50 mm. Example: 3000 − 50 = 2950 mm.
-
4.8 Width of the roof covering: rafter spacing − 22 mm. Example: 750 − 22 = 728 mm.
-
4.9 Polycarbonate tip: multiwall sheet 980 mm + 22 mm = 1002 mm spacing from rafter centre to rafter centre. polycarbonate only
Tip: This saves you from cutting the sheets on site.
05 Insert rubber seals
- Utility knife
- Mitre saw
Parts: Rubber strips 2 mm (4 mm for glass), Rafters, Gutter, Wall trim
-
5.1 Cut the rubber strip to twice the rafter length plus 10 cm.
Caution: The rubber retracts by a few centimetres after insertion. That is why you cut it longer.
-
5.2 Slide the rubber strip into the rafter.
-
5.3 Cut off the protruding rubber at the end.
-
5.4 Cut rubber strips for the gutter and wall trim (plus 10 cm) and slide them in.
-
5.5 Check the thickness: rubber 2 mm for polycarbonate, 4 mm for glass.
Caution: For glass, use the thicker 4 mm rubber.
06 Fix the wall profile
- Metal drill bit
- Hammer drill
- Spirit level
- Cartridge gun
- Cordless screwdriver
- Trestles
Parts: Wall profile, Hammer-in plugs, Silicone, Sealing tape (Compriband)
-
6.1 Lay the wall profile on two trestles.
-
6.2 Pre-drill the plug holes: first hole at 10 cm, then every 50 cm.
-
6.3 Hold the wall profile at the calculated height and align it level with the spirit level.
Caution: Bottom edge at 242 cm in the example. Use your own height from chapter 4.
-
6.4 Mark the drill holes on the wall with a pencil.
-
6.5 Drill the fixing holes in the wall.
-
6.6 Seal the wall profile against the wall with a thick bead of silicone. Sealing tape is also recommended.
Caution: The bead must run continuously all round. This evens out irregularities in the wall.
-
6.7 Screw the wall profile on with the hammer-in plugs.
-
6.8 Fill the joint between wall and wall profile with silicone, smooth it and seal it.
Caution: Do not skimp on silicone: the joint must be completely sealed.
07 Option: freestanding optional
- Spirit level
- Cordless screwdriver
Parts: Additional posts, Cross beam, End caps, Floor brackets, Additional screws
-
7.1 Erect the posts on the high side of the roof: with brackets on the floor or in a concrete foundation.
-
7.2 Align the posts vertically, then screw them down.
Caution: Vertical means: check with the spirit level.
-
7.3 Place the cross beam on the posts and fix it with self-drilling screws.
-
7.4 Fit the side caps.
-
7.5 Screw the wall profile level to the cross beam. Then continue as for wall mounting.
Caution: Make sure it is aligned level.
08 Prepare the gutter
- Hole saw
- Metal drill bit
- Cordless screwdriver
- Cartridge gun
- Hacksaw
- Tape measure
- Trestles
Parts: Gutter, Leaf guard, End caps for gutter (2), Stop angles (9), Silicone, Screws 4.2 × 19 mm
-
8.1 Lay the gutter on the trestles.
-
8.2 Drill the hole for the water outlet: hole saw 68 mm, 55 mm from the edge and from below. At both ends.
Caution: With a roof overhang, this dimension is not used: the hole is then drilled in the centre.
-
8.3 Detach the leaf guard and shorten it by 5 mm.
Caution: With a roof overhang, the leaf guard is not shortened.
-
8.4 Inject silicone into the gutter ends.
-
8.5 Insert the leaf guard into the gutter.
-
8.6 Fix both end caps with screws 4.2 × 19 mm. Do not yet screw the point marked X.
Caution: The fourth screw only goes in at the very end (chapter 16).
-
8.7 Seal the end caps with silicone.
-
8.8 Screw on the first stop angle: curve facing up, 30 mm from the gutter edge to the centre of the hole.
-
8.9 Calculate the spacing: (roof width − 60 mm) ÷ bays. Example: (6060 − 60) ÷ 8 = 750 mm centre to centre.
Caution: The same calculation applies later to the rafters.
-
8.10 Screw on the remaining stop angles (8 ×) at the calculated spacing.
09 Option: LED spots optional
- Hole saw
- Cordless screwdriver
Parts: LED set (spots, cable)
-
9.1 Determine the position of the spots on the rafters.
-
9.2 Drill the holes with the hole saw: diameter 29 or 44 mm.
-
9.3 Run the cable through the rafters and lead it on the wall side to a power connection. This only happens once you have reached the posts.
-
9.4 Insert the spots only once all rafters are installed. This way they are not damaged.
Caution: Electrical installation only by qualified installers. Otherwise the warranty lapses.
10 Gutter and side beams
- Props
- Cordless screwdriver
- Spirit level
- Tape measure
- Ladder
Parts: Props, Side beams (2), Screws
-
10.1 Set the props to the correct height.
-
10.2 Lay the gutter on the props.
Caution: Lift and lay down in pairs only.
-
10.3 Align the gutter level.
-
10.4 Insert the first side beam: slide the square-cut corner into the gutter and the mitre into the wall profile.
-
10.5 Insert the second side beam in the same way.
-
10.6 Fix the side beams under the wall profile with 2 screws each.
-
10.7 Fix the side beams to the gutter with 2 screws each.
-
10.8 Check squareness: the two diagonals A and B must be equal in length.
Caution: Very important: only a square frame can be roofed cleanly later.
11 Shorten the posts
- Tape measure
- Cordless screwdriver
- Mitre saw
- Hammer drill
- Spirit level
Parts: Floor profiles (U-profiles), Posts (3), Screws for the floor (not in the kit)
-
11.1 Determine the post positions: with a roof depth of 300 cm, the post centre is at 294.5 cm (5.5 cm less).
-
11.2 Mark the post brackets (U-profile), pre-drill holes and screw them down on the patio.
Caution: Screws for the floor are not in the kit.
Tip: If the posts stand in soil: dig holes instead.
-
11.3 Determine the length of the posts. Take the slope into account.
-
11.4 Saw all 3 posts to the determined length.
12 Post with water outlet
- Hole saw
- Hacksaw
- Cordless screwdriver
- Spirit level
Parts: Posts (3), Drain pipe DN75 (HT), Pipe bend DN75, Screws
-
12.1 Choose the post for the water outlet. Drill the hole with the 76 mm hole saw.
-
12.2 Saw the drain pipe to length: 20 mm shorter than the post at the top.
-
12.3 Slide the PVC bend into the drilled hole and turn it inwards.
-
12.4 Insert the drain pipe into the post and connect it to the bend.
-
12.5 Carefully lift the gutter a little and let the leaf guard sink into the drain pipe.
Caution: Work in pairs. Lift the gutter only slightly.
-
12.6 Slide the posts over the U-profiles: first post 1, then 2, then 3.
-
12.7 Fix each post to the gutter with 2 screws: first the outer one, then the middle, then the second outer post.
-
12.8 Align the posts with the spirit level.
Caution: Check vertical and level.
-
12.9 Pre-drill 4 holes per post (3.5 mm) and fix them to the U-profile with 2 screws per side.
13 Intermediate beams and trim
- Cordless screwdriver
- Mitre saw
- Tape measure
Parts: Intermediate beams (7 in the example), Wall trim, Screws
-
13.1 Insert the first intermediate beam between gutter and wall profile and screw it like the side beams.
-
13.2 Repeat the same until all beams are in place.
-
13.3 Measure the gaps between the beams and cut the trims to size with the saw.
-
13.4 Push the trims onto the wall profile.
-
13.5 Screw the trim to the wall profile from below (7 ×).
Tip: Optionally, the same can be done for the gutter profile.
-
13.6 Optional: insert LED spots. optional
Caution: Electrical connection only by qualified installers.
14 Prepare the roof covering
- Mitre saw
- Utility knife
- Gloves
Parts: Polycarbonate sheets, Anti-dust tape, Aluminium end profile
-
14.1 Peel back the protective film 5 cm all round at the ends. polycarbonate only
Caution: The rest of the film stays on the sheet until the end.
-
14.2 Cut the sheets to the calculated dimensions (hand saw, jigsaw or circular saw). polycarbonate only
-
14.3 Stick anti-dust tape on the front (gutter side). polycarbonate only
Caution: The tape keeps dirt out of the chambers and lets water vapour escape.
-
14.4 Place the aluminium end profile over the tape. The drip edge carries condensation away. polycarbonate only
-
14.5 Glass needs no preparation. Continue on the next page. glass only
15 Insert the roof covering
- Cordless screwdriver
- Ladder
- Gloves
Parts: Roof covering (8 bays in the example), Side cover profile (corner strip), Cover profile (round strip), Torx screws 19 × 32 mm
-
15.1 Lay the polycarbonate sheets: the aluminium end profile sits on the gutter side. polycarbonate only
Caution: The UV side always faces up. This is printed on the protective film.
-
15.2 Lay glass only with a second person. Only with gloves. Stand the ladder securely. glass only
Caution: Never carry glass alone. Mind your own safety.
-
15.3 Fix the corner strip centrally on a side beam with Torx screws 19 × 32 mm.
-
15.4 Lay the next sheet. Place the round strip on the intermediate beam and fix it with the same screws.
-
15.5 Continue from one side to the other until all bays are covered.
16 Finishing work
- Cordless screwdriver
- Cartridge gun
Parts: End seal, Wall caps (2), Screws
-
16.1 Slide the wall rubber into the wall profile.
-
16.2 Fix the wall caps to the side of the wall profile with 2 screws each.
-
16.3 Drive in the last screw of the gutter on both sides.
-
16.4 Peel the protective film off the sheets. Dispose of waste correctly. polycarbonate only
-
16.5 Done. Clean every six months, and the roof will last longer.